The work will be completed in 4 stages:
The contractor will begin at the intersection of Forest Hill Avenue and Howell Avenue. Traffic will not be able to travel east on E. Forest Hill Avenue from Howell Avenue nor turn south on Howell Avenue from W. Forest Hill Avenue.
In stage 2 the contractor will be working in the curb lane of Howell Avenue. Traffic will be reduced to one lane north bound on Howell Avenue from Groveland Drive to Drexel Avenue. The side roads will be open unless the contractor is working through the intersection.
Stage 3 is planned for a complete closure of northbound Howell between Groveland Drive and Drexel Avenue. This work will be completed at night with a detour route. One lane will remain open northbound during the day.
Stage 4 will be one lane open northbound from Groveland Drive to Drexel Avenue. The side roads will be open during this stage of work.